HBĐT) – the project of road No. 433 – directing Hoa Binh city to Da Bac district, is an important project of province. Over 6 years of deploying, the project have not yet been accomplished and the contract must be extended to December 2018. The reason that the project fell behind schedule is because of a lack of funds and entanglements in processing site clearance.
From km 1+670 to km 1+900, the length = 230
meters, there are four households addressing in May No. 4 hamlet, Hoa Binh
commune (Hoa Binh city). Although they had received full compensation of site
clearance and late payment interests, until now they have not yet handed over
the site for the construction teams.
The project of renovating and upgrading road
No. 433, particularly in a route from km 0 to km 23, was approved by People’s
Committee of Hoa Binh Province in Decision No. 2530/QĐ-UBND on 31stDecember 2010 and was allowed to adjust in Decision No.1161/QĐ-UBND on 27thAugust 2012 with the total length of route designing to 18,9 km, starting point
is km 0 at Huu Nghi ward (Hoa Binh city), and ending point is km 23+00 at Cao
Son commune (Da Bac district). The total amount of investment is 988 billion
VND ( including 691,3 billion VND for building; 35,9 billion VND for consulting
fees and others; 62 billion VND for the cost of site clearance and 199 billion
VND for contingencies). At the moment, the total capital is 578,5 billion VND
and has been disbursed completely.
Project Management Unit of Transport
Construction Works plans to perfect the ground, road surface and drainage
system on the route from km 0 to km 9+900 by 31st December 2018 in order to hand over for developing
and using. Now, the process of site clearance faces some difficulties and
entanglements which affect the construction progress.
Following the plan, the route from km 0 to km
9+900 has to be completed and come into operation in 2018. Project Management
Unit of Transport Construction Works proposed People’s Committee of Hoa Binh
Province to allocate for advancing budgetary resource, capital and other
equities with the total money of about 127,5 billion VND, aiding the
contractors building. In the process of site clearance, the relevant local
authorities are requested to focus on completing construction of resettlement
areas and finishing site clearance totally in order to hand over for
construction teams which will develop the rest parts as planning.
On 12th April of auditing date,
Chairman of the provincial People's Committee, Mr. Van Quang Nguyen, asserts
the Hoa Binh city and Da Bac district authorities to concentrate on resolving
site clearance conclusively, which
facilitates the contractors to organize
construction and strive for accomplishing project in December 2018.
Currently, Luong Son district counts 905 business establishments operating in industry and handicraft, helping generate jobs and stable incomes for local labourers.
Hoa Binh scored the highest points in two out of the eight indicators of the Public Administrative Reform (PAR) Index ranking in 2023 that the Ministry of Home Affairs announced on April 17.
A working delegation from Hoa Binh province led by Deputy Secretary of the provincial Party Committee and Chairman of the provincial People’s Committee Bui Van Khanh is attending a programme to popularise Vietnamese products in the US and Canada on April 20-28.
Anyone found to be encroaching upon the forest, even if it is just one bamboo shoot, will face penalties. This commitment has been unanimously added into the covenant of Bua Cau hamlet, Hung Son commune in Kim Boi district, to protect the forest.
The Hoa Binh Power Corporation (PC Hoa Binh) has applied synchronous measures to gear up for the coming summer season when power consumption demand surge may cause a risk of power supply disruption.